Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Greater Victoria infrastructure get millions in investments to help with economic recovery

New community spaces, health centre, turf fields coming for region

Owners say loss of parking pushes businesses to the brink

New Penny Farthing patio ‘will be like New Orleans, or Las Vegas’

Victoria International Airport rolls out health and safety initiative

YYJ limits who can enter terminal along with other added safety measures

Ryan Reynolds matching fundraising dollars for B.C.’s Great Bear Rainforest

Vancouver-born actor appeals to the public with Make Ryan Pay! campaign

Sidney neighbours host miniature Dinner en Rouge after COVID-19 cancellation

Group came together to celebrate Canada Day safely

UPDATE: Military reservist facing 22 charges after allegedly ramming gates at Rideau Hall

The man, who police have not yet officially identified, will be charged with multiple offences

Alberta health minister orders review into response after noose found in hospital in 2016

A piece of rope tied into a noose was found taped to the door of an operating room at the Grande Prairie Hospital in 2016

B.C.’s major rivers surge, sparking flood warnings

A persistent low pressure system over Alberta has led to several days of heavy rain

B.C.’s Indigenous rights law faces 2020 implementation deadline

Pipeline projects carry on as B.C. works on UN goals

‘Mind boggling’: B.C. man $1 million richer after winning Lotto 6/49 a second time

David O’Brien hopes to use his winnings to travel and of course keep playing the lottery

White-throated sparrows have changed their tune, B.C. study unveils

Study marks an unprecedented development scientists say has caused them to sit up and take note

B.C. teacher loses licence after sexual relationships with two recently-graduated students

The teacher won’t be allowed to apply for a teaching certificate until 2035

Lower Mainland teacher facing child pornography charges

Elazar Reshef, 52, has worked in the Delta School District

All community COVID-19 outbreaks declared over in B.C.

Abbotsford manufacturer cleared by Dr. Bonnie Henry

Most Read