Janelle Staite, regional deputy director with the Ministry of Transportation and Infrastructure, said commuters on the Trans-Canada Highway are looking at another six months of construction on the McKenzie interchange, bringing the project’s completion into 2020 and well past its original target date of fall 2018. (Shalu Mehta/News Staff)

Another six months of construction anticipated for McKenzie interchange

Snowfall and unexpected rock to blame for further delays

Commuters on the Trans-Canada Highway are looking at another six months of construction on the McKenzie interchange, bringing the project’s completion into 2020 and well past its original target date of fall 2018.

The Ministry of Transportation and Infrastructure announced that due to this year’s winter conditions and unexpected variable rock encountered during drilling, the project will need more time.

Janelle Staite, regional deputy director with the Ministry of Transportation and Infrastructure, said that when workers were drilling to put in piles for a pier that would support the main bridge structure, variable rock was encountered much earlier than anticipated.

The unexpected rock sent engineers back to the drawing board to redesign and reconstruct plans in order to put the pier in the same spot. Staite said this set the project back about six to eight weeks.

The record snowfall this year also got in the way of construction.

READ MORE: McKenzie interchange project sees delays

“Snowfall in any construction site slows us down to a halt,” Staite said. “We can’t work when the site is covered in many inches of snow and we have to wait until that snow is cleared to get up and running again.”

Construction schedules for the interchange have also been altered to lessen traffic and noise, which Staite said is something the ministry is keeping in mind due to the proximity of residences in the area.

So far, the second and final construction contract is about 55 per cent complete with workers focusing on building the overpass over the Trans-Canada Highway. The highway will be lowered about eight metres so vehicles can pass under the bridge but Staite said there are no concerns for flooding as engineers have ensured there will be adequate drainage in place.

“There’s lots of work happening and more to come,” Staite said. “Our hope was that by the end of summer we would have free flowing traffic on Highway 1 and have the overall project complete by 2019… the revised schedule is to have free flowing traffic by winter.”

Staite said by winter — or early 2020 — the traffic lights on Highway 1 should be removed and free flowing traffic should be able to move northbound and southbound on the highway. Those trying to make a left turn onto McKenzie Avenue will continue to do so with a traffic light in a slightly different position than where it is now.

READ MORE: Malfunctioning traffic signals to blame for significant traffic backup at McKenzie interchange

By the summer of 2020, the entire project — including the loop ramp, landscaping and transit facilities — is expected to be complete.

The effects of construction are going to be similar to what they are right now, Staite said. Once the signal at McKenzie Avenue is removed, motorists will not see a traffic light until they hit Tillicum Road.

The change in schedule does affect the $85 million budget allocated for the project.

“A delay like this and some unencountered engineering conditions certainly do change (the cost) and that’s why we’re working with a contractor to try to understand what it looks like,” Staite said. “There will be an increased cost, we’re just getting to the bottom line of what that number is.”

The Ministry of Transportation and Infrastructure will share the new cost of the project in about a month or so, Staite said.

Once the project is complete, the ministry estimates it could save commuters travelling between the West Shore and downtown communities approximately 20 minutes.

“It’s that short term pain but significant long term gain that’s going to give people an opportunity in mornings and afternoons to have a more reliable and efficient commute,” Staite said.

shalu.mehta@goldstreamgazette.com


Like us on Facebook and follow us on Twitter

 

A large crane hangs over a dig site for the McKenzie interchange project. Highway 1 will be lowered by eight metres so vehicles can pass under a bridge. The project has been delayed by another six months, bringing it’s completion date into 2020 and well past its original target date of fall 2018. (Shalu Mehta/News Staff)

Just Posted

Saanich brings Uptown-Douglas Corridor draft plan to the public

Feedback from residents will help finalize the plan

Greater Victoria could see a months worth of rain within a week this fall

Weather Network predicts wet, warm fall season for B.C.

B.C. population on pace to fall behind Alberta

Provincial population could reach almost seven million in 2043, but Alberta is growing faster

Some 5,000 residents on the Saanich Peninsula have signed up for alert system

Sidney hosts Peninsula Emergency Preparedness Exhibition Friday

‘It’s almost surreal’: B.C. fire chief, sidekick Sammy recap rescue mission in Bahamas

Chief Larry Watkinson and Sam the disaster dog spent 8 days assisting a search and rescue team

Crime Stoppers most wanted for Greater Victoria for the week of September 17

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

POLL: Should the province step in to upgrade the road to Bamfield?

The death of two University of Victoria students on a bus bound… Continue reading

Kamloops high school evacuated after receiving threat

Police have not released any further details into what the threat includes

Woman held at gunpoint during carjacking in UBC parkade

University RCMP say the vehicle is still missing, and two suspects are at large

VIDEO: Angry B.C. cyclist starts shaming dangerous drivers online

‘You motorists deserve all your costs and misery’

‘Time to take action:’ Children advocates call for national youth suicide strategy

Council wants Ottawa to make reporting of suicides and attempted suicides mandatory for data collection

Canadian inflation decelerates to 1.9% as gas prices weaken

August was the sixth straight month that price growth was 1.9 per cent or higher

Man who crushed Nanaimo RCMP cars with stolen truck gets more jail time

Majore Jackson, 34, sentenced to two more years in jail in provincial court in Nanaimo

Most Read