People look on as the Dynamic Beast Crane takes apart the last pieces of the old Johnson Street Bridge. (Nicole Crescenzi/VICTORIA NEWS)

Johnson Street Bridge may see upcoming audit

Taking over a decade to complete with a $65 million price jump

After almost a decade of work on the Johnson Street Bridge and more than a $65 million price jump, the request by Victoria Mayor Lisa Helps for an independent audit may be fulfilled.

Gordon Ruth of the B.C. Auditor General for Local Government (AGLG) responded to Helps request in a letter to say the next audit topic for his team has been identified as Capital Project Management and will consider the mayor’s request during the audit selection process.

The Johnson Street Bridge was the largest capital project in the city’s history and according to Helps “it didn’t go well.”

March 31 saw the one year anniversary of the bridge opening, and while the general consensus on the bridge is pretty positive now, it caused major turmoil throughout the building process resulting in two key policy changes being implemented.

RELATED: Victoria’s bridge-lifting job includes ‘rare’ exposure to abuse

The project management framework sets out the guidelines of all large capital projects and the estimate policy requires a third party to verify the cities work.

Helps calls the two policies the legacy of the last council and says thanks to them “we will never do another project like the Johnson Street Bridge.”

Helps says she’s curious to see what other recommendations an audit could make if it did end up going forward, adding the findings could help other local governments with their own large capital projects.

RELATED: Investigation into Johnson Street Bridge fall to evaluate safety measures

Johnson Street Bridge timeline:

Preliminary work beginning in April 2009 when Victoria city council made the decision to replace the old Blue Bridge, which was deemed a ‘very significant heritage landmark.’

The debate over whether to replace or rehabilitate the bridge ensued and it wasn’t until August 2010 that council voted in a near unanimous vote to replace.

In January 2013 the City of Victoria signed a fixed-price contract of $63 million to replace the old Johnson Street Bridge by the spring of 2016. The project was dubbed the largest capital project in the City’s history.

Fast forward to March of 2014, Jiangsu, a Chinese steel manufacturer, begins to fabricate major parts of the bridge. A few months later in July of the same year Victoria receives word the steel and fabrication are sub-par causing the anticipated completion date for the bridge back to January 2017.

RELATED: Six protesters arrested in Victoria’s Johnson Street Bridge sit-in

In April 2016 Victoria councillors were asked to approve $8.2 million for the project, bringing the cost to $105.06 million, $42 million more than the original budget. Two months later the City’s senior project manager was removed from his position.

In February 2017, the project is awarded the most wasteful project of the year, citing the $42 million increase on what started as a $63 million project.

Finally in August 2017 the first shipment of steel for the new bridge arrives with the final shipment arriving in September 2017. A gigantic crane barge called The Dynamic Beast, arrived in Victoria in December 2017 and again in January 2018 to finish assembling the bridge. In February 2018 the new Johnson Street Bridge is raised for the first time.

On March 31, 2018 the bridge opened to vehicle traffic for the first time.



kendra.crighton@blackpress.ca

Follow us on Instagram
Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

Construction workers lift one of the 290-tonne steel rings for the new Johnson Street Bridge into the air at the Point Hope Shipyard using the giant crane the Dynamic Beast on Friday morning. The rings are being placed onto the barge and will begin installation at new bridge site tomorrow (Lauren Boothby/VICTORIA NEWS)

Johnson Street Bridge is lifted for the first time. (File Photo/Victoria News)

The new Johnson Street Bridge, here with the current bridge in the background, opened officially on March 31, 2018 with a community celebration. (Don Descoteau/Victoria News)

Construction leaders who worked on the Johnson Street Bridge project, along with a junior member of the team, prepare to see the structure opened on March 31. (Spencer Pickles/Black Press)

Just Posted

Organizers seek input for long-awaited Oaklands community garden

Oswald Park Community Garden Design Workshop coming up on Jan. 19

Six months to Francophone Games, 600 volunteers needed

Online applications open on Jan. 14

Tech consortium invests $25 million into four University of Victoria research projects

Investments come with goal of developing, implement technologies created by Canadians

Mass-timber project in Esquimalt switches from condos to rentals

Corvette Landing will now offer rental units in the area

After cashing in on QB gambles, Chiefs and 49ers to clash in Super Bowl

KC beats Tennessee, San Francisco dispatches Green Bay to reach NFL title game

B.C. VIEWS: Few clouds on Horgan’s horizon

Horgan’s biggest challenge in the remainder of his term will be to keep the economy humming along

B.C. forest industry grasps for hope amid seven-month strike, shutdowns, changes

Some experts say this could be worse for forestry than the 2008 financial crisis

Northern B.C. RCMP investigating alleged sexual assault in downtown Smithers

One person was transported by ambulance to hospital following RCMP investigation at Sedaz

UBC, Iranian-Canadian community create memorial scholarship in honour of victims

The Jan. 8 crash killed 176 people, including 57 Canadians

Disrespectful that Horgan won’t meet during northern B.C. tour: hereditary chief

Na’moks said he was frustrated Horgan didn’t meet with the chiefs

Canucks extend home win streak to 8 with 4-1 triumph over Sharks

Victory lifts Vancouver into top spot in NHL’s Pacific Division

Most Read