Saanich expects to replace Craigflower bridge in the summer of 2013

Saanich aims to replace Craigflower bridge next June

Craigflower Bridge will be well into its 80th year of service when Saanich begins its replacement project

Craigflower Bridge will be well into its 80th year of service when Saanich begins its replacement project, now slated for the summer of 2013.

While the original timeline for joint Saanich-View Royal project was to have work start this summer and running into the fall, municipal engineers were forced to put the project on hold while they awaited federal environmental and archaeological permits.

Initially there was talk about construction potentially running from the winter through to spring, but those plans were scrapped due to the holidays.

“We heard a lot of feedback from local businesses that the loss of (access during) the Christmas shopping would be devastating,” said Jim Hemstock, Saanich’s manager of transportation. “And it also didn’t give us summer holidays, looking after getting the school kids back and forth. Those two were good reasons to go with the summer schedule.”

While Hemstock anticipates the permits will be issued in August, he says the Department of Fisheries and Oceans will have the final say on when construction can take place.

“We’re expecting it to be June 1, 2013. It could be slightly different, but I believe that going to be the window they’ll give us,” he said. “By June 1 the herring have finished their run and the salmon don’t start until Sept. 15. That’s what drives the window”

Engineers are currently completing the final design of the bridge, and Hemstock says they’ll be pre-qualifying contractors in the fall, to send the project to tender in February.

“We’re thinking we’re going to give the folks a long time to work on their bid – hopefully that will lead to better pricing,” he said.

The $10.7-million Craigflower Bridge reconstruction project is funded mostly by federal gas tax cash ($10 million). Saanich will cover 60 per cent of the remaining bill, and View Royal will cover the rest.

The existing narrow, two-lane bridge is 79 years old. It’s slated to be replaced by a three-lane bridge, complete with bike lanes and wide sidewalks.

Saanich will also simultaneously replace sewer infrastructure along Gorge Road, between Admirals and Tillicum roads, during the bridge construction. That would require Gorge Road to be shut down completely, too, during that time.

kslavin@saanichnews.com

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

UPDATED: Young deckhands backed out of fatal Arctic Fox II trip just before fishboat departed

Inexperienced twin brothers had ‘gut feeling’ and bailed before going to open ocean

Police investigating alleged assault on Oak Bay Avenue

Staff at Oak Bay Home Hardware say one person was taken to hospital

Oak Bay neighbourhoods rocked by blasting activity

Oak Bay seeks new rock blasting bylaw regarding ‘continuous’ noise

Greater Victoria hardly making a dent in greenhouse gas emissions target

One-per-cent drop from 2007 to 2018 a far cry from the 33-per-cent goal for 2020

VIDEO: Seal pup and mom play and ‘kiss’ in Oak Bay Marina

BRNKL seal cam captures harbour seal growing up in busy harbour

B.C. records new COVID-19 death, 85 more cases; Horgan calls on celebrity help

This brings the total number of active confirmed cases to 531 across the province

Horvat scores 2 as Vancouver Canucks beat Blues 5-2 in NHL playoff opener

Game 2 in best-of-seven series goes Friday night

Old-growth forest defenders in Campbell River call for B.C. forest minister’s resignation

Protestors outside North Island MLA’s office ask government to stop old-growth logging

Teachers to get 2 extra days to prepare for students’ return, now set for Sept. 10

Students will first start with orientation and learn rules of COVID-19 classroom policies

High-volume littering at Cape Scott draws ire from hiking groups

Popular Vancouver Island hiking spot not closing, but frustration about crowding grows

SFU to drop ‘Clan’ varsity team name

The ‘Clan’ name is shortened from ‘Clansmen,’ and was introduced roughly 55 years ago

New Tory leader must build a strong team in Commons and for the campaign: Scheer

Scheer marked his final day in the House of Commons today as leader of the Opposition

B.C. to hire 500 more COVID-19 contact tracers ahead of fall

Contract tracers add an ‘extra layer’ in the fight against the novel coronavirus

Feds commit $305M in additional funds for Indigenous communities during COVID-19

Money can be used to battle food insecurity and support children and mental health

Most Read