G.P. Vanier in Courtenay. Circa 2018. Photo courtesy Comox Valley Schools

Vancouver Island school upgrade $1.4 million over budget and no one noticed

The original construction budget was not adjusted to account for some expenses

Following the completion of the Georges P. Vanier seismic upgrades in October, the school district determined they had gone approximately $1,450,000 over budget.

The $33.1 million upgrade project started in 2016 and was completed in phases, including adding additional classrooms, specialized spaces such as a new auditorium and an Aboriginal education room, and relocating the library. The project also included upgrading the school’s mechanical and electrical systems that were nearly 50-years-old. Approximately $32.8 million for the project was provided by the Ministry of Education and around $1 million was from the school district.

According to SD71 secretary-treasurer Nicole Bittante, the school district did not realize they were over budget until the project was completed as they thought all expenditures had been accounted for.

“While this overspend was not identified until the project was completed, it was thought all along that the budget allowed for these expenditures,” said Bittante. “District staff were reconciling all of their amounts to the original budget. In the meantime, the original budget hadn’t been adjusted for various items. So it appeared during the term of the project that the project was on schedule and on budget.”

Bittante outlined the areas where the overspending happened, with the most significant portion being the GST.

“The original construction budget back in 2015 that was provided to the construction company did not include GST, however, the budget should have included the non-rebatable portion of GST,” she said. “There’s a portion that the district pays and then receives back in a rebate.”

The non-rebatable portion of GST was a cost to the district of approximately $477,000.

Other areas where there was overspending included a portion of the director of operations’ salary and some wages for a custodian which were not reduced from the construction budget, totaling $196,000.

In 2017, the gymnasium walls required repairs due to a safety concern, and while the Ministry provided $220,000 to address the issue, the fix still went $117,000 over budget.

The costs for the initial project planning, totaling approximately $152,000, were also not removed from the construction budget. Another $40,000 was listed as “other balancing factors,” and the project went an additional $465,000 over budget as this amount was not covered by the risk reserve.

“The $33 million included a $4 million risk reserve. It wasn’t guaranteed funding, it was an amount that was awarded through the ministry, but it was an amount that we had to apply for and there were criteria attached to it,” said Bittante. “I think the issue is that we, in our budget, gave the $4 million to the construction company and it was spent.”

The school district was only able to access approximately $3.5 million of the $4 million with the rest being a cost to the district.

Bittante clarified that the overspending was not a reflection of the contractor as they came in on budget. Their budget just should have been smaller.

“They came in on target with money that they were given, but we weren’t able to access all the funds.”

She adds that increased oversight will occur on all future capital projects to ensure any overspending is identified and taken care of immediately.

At Tuesday’s meeting, the SD71 school board voted in favour of transferring $1,450,000 of unrestricted operating surplus to cover the overspend.

Just Posted

Salmon counts may indicate future fishing closures

Total numbers of chinook continue to be in decline, says DFO

Access: Technology lags for people with vision, hearing impairments

Accessibility barriers addressed at the Pacific Training Centre for the Blind

Saanich police arrest man who spat on, pulled knife on man who refused to give him a cigarette

Police recommend the 18-year-old be charged for assault with a weapon

Chilean teen brings protest to Victoria streets

Chile’s peaceful protest unseen, says visiting student

Chef recalls ‘attic full of smoke’ during Four Mile restaurant fire Tuesday

Food saved as power restored to the eatery around noon Wednesday

WATCH: Artist explains inspiration behind new Oak Bay mural

Oak Bay’s Parade of Play mural might be the biggest in Greater Victoria

POLL: Are you satisfied with the result of the federal election?

The ballots have now been counted and the dust has settled on… Continue reading

Greater Victoria wanted list for the week of Oct. 22, 2019

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

B.C. parents sue city and province in 12-year-old daughter’s drowning at lake

Beverly Park drowned at Rotary Lake in Dawson Creek in August 2016

Island mom warning others as suspicious powder found in mail

“I was very uneasy … it could be coffee whitener or it could be something else in the bag.”

VIDEO: Chill with polar bears through an Arctic live cam

Cam reopens just ahead of Polar Bear Week

Aquilini companies deny negligence in U.S. vineyard fire that killed two kids

Fire occurred at Red Mountain Vineyard, located in southeast Washington State

Surrey cop killer gets new parole conditions

Surrey RCMP Constable Roger Pierlet, 23, was shot dead on March 29, 1974

Most Read