Sewage treatment project will hit cost overruns

Taxpayers need to continue to ask questions of the CRD and the sewage treatment project, writes Tony Rose

The public should be aware that the much publicized cost of $780 million for regional sewage treatment is not much more than a guestimate, plus or minus 25 per cent at best.

A 25 per cent increase in cost on this project will almost double the amount the local taxpayer has to fund.

In discussions with the CRD, it seems as if very little of the necessary detailed engineering to produce a definitive estimate appears to have been done.

There are doubts about the ability of the CRD to give “due diligence” to a project of this nature and size on behalf of the taxpayer.

Recent large municipal projects have had overruns well in excess of that 25 per cent, and there is no reason to believe that the sewage project will be any different.

Bear in mind, too, that this plant has a finite life. It is designed to last 25 years, at which point all or part of it will need to be replaced. Like your car, it wears down.

If there is a decision to go ahead, then the most reasonable and least painful way to introduce water treatment would be to phase it in over a period of 25 years with smaller modular plants at say, three year intervals, costing no more than $50 to 80 million each.

It’s still a substantial investment, but certainly a better way to control cost overruns, and which gives you the opportunity to see if and how it works.

We need to continue to ask questions of the CRD, and request a public forum with their engineering department to better understand their capabilities and how they propose to conduct this project.

Tony Rose, Saanich

 

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Environment Canada has issued a wind warning for Greater Victoria, with winds expected to get up to 70 km/h Friday morning. (Don Denton/Black Press Media)
Wind warning promises blustery Friday for Greater Victoria

Winds up to 70 km/h expected Friday morning

Passengers in rows 13 to 19 on Air Canada Jazz flight 8069 from Vancouver to Victoria Feb. 28 were exposed to a case of COVID-19. (THE CANADIAN PRESS/Nathan Denette)
COVID-19 exposure found on flight from Vancouver to Victoria

Passengers in rows 13 to 19 on Air Canada Jazz flight 8069 Feb. 28 affected

Low interest rates have acted as a catalyst for the pandemic real estate market. (THE CANADIAN PRESS/Graeme Roy)
Real estate sales surging across Greater Victoria but risks lie ahead

Single family home prices jump nine per cent over past year while condo values remain stable

Crews deal with a rock slide on the Malahat section of Highway 1 in 2017. (Black Press Media file photo)
Rock work closes Highway 1 in Langford for spurts

Friday closures could delay drivers up to 20 minutes

Crews disassemble the iconic red and white KFC bucket from a sign on Goldstream Avenue. (Photo courtesy of Mark Schoor)
Iconic KFC bucket removed from Goldstream Avenue

Popular fast-food chain closes Langford location

B.C. Health Minister Adrian Dix and provincial health officer Dr. Bonnie Henry head for the B.C. legislature press theatre to give a daily update on the COVID-19 pandemic, April 6, 2020. (B.C. government)
B.C. nears 300,000 COVID-19 vaccinations, essential workers next

564 new cases, four deaths, no new outbreaks Thursday

Anyone with information on any of these individuals is asked to call 1-800-222-TIPS (8477) or visit the website victoriacrimestoppers.ca for more information.
Greater Victoria Crime Stoppers wanted list for the week of March 2

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

(Black Press Media file photo)
POLL: How’s your butter?

Recent reports have some Canadians giving a second look to one of… Continue reading

The intersection of Melrose Street and Third Avenue. (ELENA RARDON / ALBERNI VALLEY NEWS)
Suspect in custody after two pedestrians struck in Port Alberni hit and run

RCMP asking for video footage, credit witnesses for quick arrest

(National Emergency Management Agency)
No tsunami risk to B.C. from powerful New Zealand earthquake: officials

An 8.1 magnitude earthquake shook the north of New Zealand Thursday morning

Comox Valley RCMP had access to 20 Street blocked off between Cousins and Choquette avenues as they conducted a raid of a house on the block. Photo by Terry Farrell
Comox Valley RCMP raid Courtenay problem house, several arrests made

Comox Valley RCMP conducted a raid of a problem house on 20th… Continue reading

(AP Photo/Richard Vogel, File)
Pandemic stress, isolation key factors as to why Canadians turned to cannabis, alcohol

Study found that isolation played key role in Canadians’ substance use

A Cowichan Valley mom is wondering why masks haven’t been mandated for elementary schools. (Metro Creative photo)
B.C. mom frustrated by lack of mask mandate for elementary students

“Do we want to wait until we end up like Fraser Health?”

(Pxhere)
B.C. research reveals how pandemic has changed attitudes towards sex, health services

CDC survey shows that 35 per cent of people were worried about being judged

Most Read