Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Cook Street Village grocery icon closing, new owners plan major renovation

Louie family has operated Oxford Foods and predecessor for five decades at Cook and Oxford streets

WorkSafeBC investigating death at Victoria Customs House construction site

Prevention officer will ensure all safety issues addressed before work starts again

Three years for serial bank robber who hit Sidney branch

Lucas Bradwell was wanted for robberies in Sidney, Abbotsford and Vancouver

PHOTOS: Gallery explores ‘broken promises’ during Japanese Canadian internment in 1940s

‘Broken Promises’ to acknowledge the thousands of Japanese Canadians who faced dispossession

POLL: Do you agree with the decision to call a provincial election for Oct. 24?

British Columbians will put their social distancing skills to the test when… Continue reading

Rare fish washes onto Whiffin Spit in Sooke

Deep water fish identified as ‘King-of-the-salmon’

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

BC Liberal Leader talks drug addiction in the Lower Mainland

Drug addiction and public safety a top priority says Andrew Wilkinson

Island Corridor Foundation launches survey on importance of Vancouver Island rail

“ICF remains 100 per cent committed to the restoration of full rail service on Vancouver Island”

Island RCMP remind drivers not to text after 19 tickets handed out in 90 minutes

The $368 fines were handed out Tuesday on Norwell Drive and Old Island Highway in Nanaimo

Vanderhoof’s Brian Frenkel takes on top job in tough times

We can get through this, new local government leader says

Most Read