Up and Up: Mitigating risks drives Johnson Street Bridge project costs higher

Engineering firm explains cost escalation in bridge project from $77M to $92.8M

A welder works on deconstruction of the Johnson Street rail bridge. Pieces are being loaded onto a barge in the waterway under the bridge. The estimated construction cost of the replacement traffic bridge took a jump this week.

Ten days after Victorians learned they’d received an extra $16.5-million federal grant for the Johnson Street Bridge replacement, the cost of the project rose by approximately the same amount.

City staff announced earlier this week that the estimated cost has jumped from $77 million to $92.8 million.

Mayor Dean Fortin called the revised budget “surprising, and frustrating and disappointing.”

“It’s lost opportunity on the funding we received from the federal government,” he said.

This morning, after the News’ press deadline, council is considering options for proceeding with the project.

Back in 2010, engineering firm MMM Group assured council that a 15-per-cent contingency would be ample to cover any unknown construction costs.

It turns out, there were many unforeseen costs of other kinds that pushed the project estimate higher.

“There are a number of significant risks on the project that we understand better now than we did two years ago,” Joost Meyboom, an engineer with MMM Group. “Those risks need to be mitigated and the cost of that mitigation is the cost increase that we’re talking about.”

Take the Telus duct relocation project announced in October, for example. MMM negotiated with the utility to move the communications duct to avoid the very expensive risk of cutting it during construction.

The new, more cautious plan had an estimated budget of $2.4 million. Now that the city’s portion of the work is complete, the actual cost has proven quite a bit higher: $3.7 million.

Another pricey addition to the budget resulted from a geophysical survey conducted by MMM in early 2011. It mapped out the floor of the Inner Harbour and discovered the bedrock varies much more widely than expected. The survey, however, is only a snapshot.

“To go to construction with that level of information is risky,” said Meyboom.

“If it’s wrong … you’re going to have a contractor out there for $3,000 an hour standing by while they figure out where the bedrock really is.”

Therefore, MMM recommends spending more money up front on a detailed drilling map.

Other rising costs include environmental mitigation strategies, archeological monitoring, the change back to GST and PST and more city support, including communications.

The new $92.8-million estimate includes a 10-per-cent contingency.

The escalation isn’t the first time taxpayers have been hit with this kind of news.

In June 2010, Meyboom announced the project’s estimate had jumped from $63 million to $89 million. Council responded by removing the rail portion of the new bridge to cut costs.

Critics of the bridge project question whether this latest increase in cost estimates will be the last.

“We’re very early on in the design process. We’re a long way from starting construction,” said Paul Brown, who ran unsuccessfully for councillor in a 2010 byelection and for mayor in the 2011 election.

The risks in these types of projects tend to escalate as they progress, he added.

So, are the biggest risks mostly behind us?

“We would like to think that given the level of due diligence that we’ve done, that we have identified all the major risks on this project,” said Meyboom. “That being said, you never know what you don’t know.”

Please visit www.vicnews.com for updates on council’s discussion of the bridge project.

rholmen@vicnews.com

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

UPDATED: Pat Bay Highway blockade ends three hours later

About 80 people from four major Peninsula First Nations blocking major highway

Central Saanich Police prepared for afternoon shut-down of Highway 17

Sgt. Paul Brailey questions efficacy of protest

City of Langford rebrands, announces several projects

‘Langford, where it all happens’ is the City’s new slogan

Fiddler on the Roof brings timely message to Oak Bay stage

Musical starts Friday in Dave Dunnet Theatre

VIDEO: Province promotes ‘lifting each other up’ on 13th annual Pink Shirt Day in Victoria

Students, MLAs, community members gathered at B.C. Parliament Buildings Wednesday

Greater Victoria Crime Stoppers wanted list for the week of Feb. 25

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

Prepare for new coronavirus like an emergency, health minister advises

About 81,000 people around the world have now become ill with COVID-19

B.C. residents in Wet’suwet’en territory have right to police presence: Public Safety Minister

Nevertheless, Bill Blair said officials remain ‘very anxious’ for the barricades to come down

Winnipeg police investigating graffiti on RCMP and other buildings

Manitoba Justice Minister Cliff Cullen denounced the vandalism

B.C. seniors’ watchdog calls for better oversight after recent problems at Retirement Concepts care homes

‘There is no financial incentive right now to be a good operator’ - Isobel Mackenzie

Trucking company fined $175K for Kootenay creek fuel spill

Decision handed down last Friday in Nelson court

B.C. Liberals call for ban on foreign funds to pipeline protesters

Sierra Club, Wilderness Committee back Coastal GasLink blockades

Most Read