Construction on Victoria’s Bay Street Bridge set to begin

Five months of construction to start on May 13

Construction on the Point Ellice Bridge, more commonly known as the Bay Street Bridge, is set to begin the week of May 13.

The City of Victoria appointed the winning tender, Seismic 2000, to take on the $6.1 million project. The federal and provincial governments are paying $2.4 million, while the rest is coming from the city’s infrastructural funding reserves.

“There’s a few elements to the project,” said Philip Bellefontaine, City of Victoria assistant director, transportation. “We’ll be stripping off old paint from the steel structure, and replacing any areas with rust. That steel will then be repainted. We’re also removing the asphalt pavement and repairing the concrete bridge deck underneath.”

ALSO READ: Johnson Street Bridge may see upcoming audit

Anodes will be installed to deter corrosion, and then the road will be repaved.

The project is expected to take five months, with eastbound vehicle traffic closed throughout the duration.

“If you are a pedestrian you will be able to travel in both directions, and cyclists can use the eastbound direction but they will have to get off the bike and walk across,” Bellefontaine said. Waterway traffic will not be affected.

ALSO READ: Historic Victoria site plagued with hefty trash dumps

Alternative traffic routes to access Vic West and Esquimalt will include the continued use of the Johnson Street Bridge, as well as Tillicum and Admirals Roads.

BC Transit services have already been rerouted to avoid the Bay Street corridor, and emergency responders have also been consulted about alternative routes.

Noise should not be a large issue during the project.

“We do acknowledge there’s going to be an impact,” Bellefontaine said. “Part of our approach is to make sure we give the travelling public as much information as possible ahead of time.”

The project is set to be complete at the end of October 2019.

nicole.crescenzi@vicnews.com

City of VictoriaConstruction

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Greater Victoria tourism industry ‘can’t wait any longer’ for financial aid

Saanich mayor, business owners call on provincial, federal governments for tourism-specific aid

COVID-19 demolishes new construction in Greater Victoria

Value of new building permits in Greater Victoria drop more than 37 per cent

Group desperate to find solution to wrecks lining shores of Cadboro Bay

Caddy Bay ‘a wild west’ without authority, say locals

Pool deck turns patio as Saanich restaurant cooks up creative outdoor seating options

District supports local businesses such as The Lakes Restaurant in creating seating

No architect for Langford building ruled ‘unreasonable’ by B.C. Supreme Court

Legal action brought against City in 2019 for permit issued on Hoffman Avenue building

If Trudeau won’t stand up to Trump, how will regular people: Singh

Trudeau did not directly answer a question about Trump’s actions amid protests

POLL: Are you sending your children back to school this month?

Classrooms looked decidedly different when students headed back to school for the… Continue reading

VIDEO: Internal investigation into aggressive arrest by Kelowna Mountie

A video allegedly shows a Kelowna Mountie striking a man several times

Gold River ready to welcome visitors and restart local businesses

In contrast to single-industry remote communities, Gold River’s diversified economy might help it better survive after reopening

22 new COVID-19 test-positives, one death following days of low case counts in B.C.

Health officials urged British Columbians to ‘stand together while staying apart’

John Horgan says COVID-19 restrictions won’t be eased regionally

B.C. Liberals urge ‘tailored’ response based on infections

Feds get failing grade for lack of action plan on anniversary of MMIWG report

‘Instead of a National Action Plan, we have been left with a Lack-of-Action Plan’

Search and rescue crews help locate 62-year-old Nanoose Bay mountain biker

RCMP: Man got lost on trail and did right thing by calling for assistance

B.C. ranchers, lodge operators say Indigenous land title shuts them out

Tsilhqot’in jurisdiction affects grazing, access to private property

Most Read